Weekly Main Street Utility Improvements

Please click on the link below to view the July 15, 2013 Main Street Utility Improvements Weekly Update.

July 15, 2013 Weekly Main Street Utility Improvements

Wednesday, July 3, 2013

Central Business District (CBD) Meeting

Central Business District (CBD) Meeting
Wednesday, July 10, 2013
8:00 a.m.
Waunakee Village Hall
Lower Level
500 West Main Street
Waunakee, WI 53597

Weekly Update - Main Street Utility Improvements

Please click on the link below to view the July 8, 2013 Main Street Utility Improvements Weekly Update.

July 8, 2013 Weekly Main Street Utility Improvements

Thursday, June 27, 2013

Thursday, June 20, 2013

Friday, June 14, 2013

Thursday, June 6, 2013

Friday, May 31, 2013

Friday, May 24, 2013

Monday, May 20, 2013

OCR Approval and Moving Forward

On May 9th the Office of the Commissioner of Railroads issued an order which essentially gives the thumbs-up to Option 2.3 as had been found acceptable to the Village Board and businesses in the area. For anyone interested in seeing what an OCR order actually looks like, you can view the May 9th order by clicking here. It's not the most exciting reading of all time, but it certainly accomplishes what we were hoping for. The Village wishes to thank our state legislators, DOT Secretary, DOT Staff, Bill McCoshen, and others who worked hard to move this process along quickly.

The DOT, Village staff and others are now working diligently to move forward with plans for project construction in 2014. The Village's Central Business District task force is meeting on May 29th to finalize plans for the streetscaping work, and the DOT recently held a progress meeting regarding technical aspects of the project.

Now that timing is better understood and that last piece of the design puzzle is approved, I will schedule another meeting on the Sustain Main Campaign. This relates to our work to best market our downtown commercial businesses, protect the residential-sensitive areas, as well as install appropriate signage for motorists and pedestrians during construction. Feel free to contact me by email or at 850-5227 if you'd like to help our efforts to "sustain main" during construction in 2014.

QUICK REMINDER - I will be at the Chamber Depot tomorrow, Tuesday, May 21st, at 8:30 AM for the Tuesday Morning Briefing on Main. Anyone interested in stopping by with questions about the Main St. project are welcome.

Thursday, May 16, 2013

Friday, May 10, 2013

Thursday, May 2, 2013

Friday, April 26, 2013

Thursday, April 18, 2013

Tuesday, April 16, 2013

Village Board Endorses Option 2.3

This Monday night, April 15th, the Village Board gave approval to Option 2.3 for the Main Street project. The next step is for the Office of the Commissioner of Rail (OCR) to consider approval of this option. We are very hopeful that this will occur, and occur quickly enough so the project moves forward for 2014 construction. The Village does not know the timing for the OCR process, but will report more information via the blog as it becomes available. See prior blog posts for a description o Option 2.3.

Monday, April 15, 2013

Briefing Reminder

Reminder: Tuesday Morning Briefing on Main. Tomorrow, Apr. 16th, 8:30 AM at the Chamber Depot. Village Administrator Todd Schmidt will report on the outcome from Monday's Village Board meeting, and fill folks in on a recent visit with the DOT Secretary.